What do the regulations require, whatever the lease says?
These rules apply whatever the drafting says.
| Rule | What it says | Where the lease comes in |
|---|---|---|
| The letting ban (regulation 27 of the 2015 MEES Regulations) | A landlord must not let a sub-standard non-domestic property unless an exemption applies: new lettings, renewals and extensions from 1 April 2018, continuing lettings from 1 April 2023 | The duty is the landlord's; the lease decides whether the landlord can get the works done |
| The valid EPC (regulation 22) | Sub-standard means a valid EPC below band E, and an EPC is valid if lodged in the last 10 years with no later EPC for the property since | Any later EPC replaces the one the landlord relies on |
| Access (regulation 45 of the 2012 EPC Regulations) | Everyone with an interest in, or occupying, the building must give the appointed assessor reasonably necessary access and co-operate | A clause can add notice, information and the areas covered |
| Lease duties survive (regulation 2(4)) | Nothing in the MEES Regulations affects a duty to carry out works, including improvements, imposed by a tenancy agreement | Repair and improvement covenants keep working alongside MEES |
The lease is also evidence. The government's landlord guidance says a compliance notice can ask for the EPC that was valid when the property was let and the tenancy agreement used for the letting.
This guide is general information, not legal advice. A solicitor drafts the lease, and the department responsible for MEES says it cannot give legal advice either, because interpretation is a matter for the courts. The landlord's side of the rules is set out in commercial EPCs for landlords.
Which clauses deal with the EPC itself?
The landlord must make sure a new tenant receives a valid EPC; who pays for a commercial EPC covers the cost. The clauses worth agreeing are about control, access and information. The Better Buildings Partnership (BBP) publishes a model EPC clause that it says mirrors clause 6.7 of the Model Commercial Lease, with two paragraphs added:
- Who may commission one. The tenant must not commission an EPC unless the 2012 Regulations require it, as they can on a sub-letting; the landlord may then approve the assessor or charge the tenant its own costs of commissioning one. The BBP cites the variable quality of EPCs and landlords' MEES liabilities.
- Access and information. The tenant co-operates with an EPC the landlord commissions, supplies plans it holds and gives the landlord's assessor reasonable access.
- Reference numbers. Each side tells the other, on request, the reference number of any EPC it commissions, so neither is surprised by a new certificate on the register.
- A rating covenant. The tenant must not do or permit anything that may adversely affect the EPC rating of the premises.
Which clauses decide whether improvement works happen, and who pays?
A right to enter for repairs may not cover improvements, so for works inside the let premises the tenant's consent shapes the MEES position.
Regulation 31 lets a landlord register a consent exemption where the tenant refuses consent to a relevant improvement, or a third party such as a superior landlord or a lender with a charge refuses despite reasonable efforts. If the tenant refused, the exemption ends when that tenancy ends; the guidance says it lasts five years or until the current tenancy ends or is assigned. The evidence is correspondence showing that consent was needed, sought and refused.
The drafting changes that picture. The BBP's clause extending the landlord's right to do works warns that an absolute right to carry out works in the premises means the landlord cannot rely on a lack of tenant consent for the exemption, and that a right needing consent not to be unreasonably withheld may not support it either if the tenant withholds consent unreasonably.
Cost is the harder negotiation. The BBP says the cost of works inside the premises is unlikely to be recoverable through a service charge, and considers it reasonable for a tenant to contribute to the extent it enjoys the savings, for example through a fixed contribution agreed at heads of terms or a payback calculation. The who-pays guide sets out what the RICS service charge standard says.
Timing matters too. The government's interim response of 18 June 2026 dropped the proposed interim EPC C milestone for 2027, saying this gives landlords and tenants more time to improve their buildings in a way that suits their buildings and lease agreements. It proposes EPC B from 2031 for private rented buildings over 1,000 square metres, where cost effective. That is still a proposal needing secondary legislation, and when checked on 10 November 2026 the consultation page showed no update after June.
Which clauses stop the rating getting worse?
- Tenant alterations. The BBP's addition to the alterations clause asks for drawings and specifications detailed enough to assess the effect on the EPC rating before work starts, the landlord's written consent to alterations expected to harm it, and as-built drawings and specifications afterwards. Its reasoning: alterations that do not need a new EPC can still lower the next one, after the current certificate expires.
- Fit-out. That clause does not cover the tenant's initial fit-out, which the BBP says is usually dealt with in the agreement for lease and a licence for alterations, so the same tests belong there.
- Landlord's works. A tenant can ask for the mirror image: BBP wording that stops the landlord, except in an emergency, carrying out works expected to harm the EPC rating without the tenant's consent.
- Improvements by the tenant. The Chancery Lane Project publishes an England and Wales alterations clause meant to let tenants make environmental improvements knowing the landlord must act reasonably.
What about energy data, renewal and the end of the lease?
Data. The seven-year payback test values an improvement's savings using unit energy costs from the landlord's bills for the property where it has them, or otherwise its supplier's unit price (regulation 28), so knowing the building's real energy use and prices helps a landlord judge which measures are required. The BBP's data sharing clause has both parties share at least energy, water and waste data and keep it confidential, and lets the landlord obtain the tenant's consumption data from its suppliers.
Renewal. MEES applies when a lease is renewed or extended, as the lease renewal guide explains. If the parties cannot agree the terms of a new tenancy under Part 2 of the Landlord and Tenant Act 1954, the court decides them, having regard to the terms of the current tenancy and all relevant circumstances (section 35). New EPC and MEES clauses are easiest to add when both sides agree them.
Lease end and dilapidations. A blanket reinstatement covenant can strip out alterations that helped the rating. The BBP's yield-up clause has the landlord give notice of alterations that need not be removed and, in deciding, have due regard to any harm removal would do to environmental performance, unless its plans for re-use or re-letting need the removal. As-built information on tenant works also lets the landlord's next EPC record them.
Where can you find published model clauses?
| Publisher | What it publishes | EPC and MEES coverage |
|---|---|---|
| Better Buildings Partnership, a collaboration of property owners | The Green Lease Toolkit, first launched in 2008, updated in 2013 and significantly updated in January 2024, with light, medium and dark green options for some clauses | EPCs, landlord's works, alterations, data sharing, service charge and yield-up. Written for multi-let offices but adaptable to other assets |
| Model Commercial Lease, originally commissioned by the British Property Federation | Template agreements for lease and leases; version 1.9 since 7 August 2026 | The EPC clause the BBP's mirrors; its April 2025 update came with a note on including Green Lease Toolkit provisions |
| The Chancery Lane Project, a UK registered charity | Climate clauses tagged by jurisdiction | England and Wales clauses on tenant alterations and on green service charge provisions |
A model clause is a starting point for the solicitors on each side, not a substitute for the regulations. For a rating check before heads of terms, you can send an enquiry through the form on this site, and landlords can read more on their EPC and MEES duties.
Sources
- MEES Regulations 2015, regulations 2, 22, 27, 28 and 31; EPB Regulations 2012, regulations 6 and 45; Landlord and Tenant Act 1954, section 35, legislation.gov.uk, checked 10 November 2026
- MEES landlord guidance (updated 5 May 2026), interim response of 18 June 2026 and consultation page, DESNZ; guide to EPCs for non-dwellings, MHCLG, GOV.UK, checked 10 November 2026
- Green Lease Toolkit pages, Better Buildings Partnership; Model Commercial Lease website; The Chancery Lane Project clause pages, checked 10 November 2026
Common questions
Can a lease make the tenant responsible for MEES compliance?
No. Regulation 27 puts the letting ban on the landlord. A lease can oblige the tenant to give access, share information, protect the rating or contribute to costs, and regulation 2(4) keeps such works duties in force alongside MEES.
What happens to a consent exemption when the tenant changes?
Where it rested on that tenant's refusal, it ends with that tenancy under regulation 31. The guidance says the landlord must then try again to improve the rating or register a further exemption.
Do these clauses work in Scotland or Northern Ireland?
Not as written. The MEES Regulations cover England and Wales, and the government's EPC guide says buildings in Scotland and Northern Ireland are subject to separate regulatory requirements, so clauses drafted around MEES need adapting there.