epcforbusinesses.co.uk

SBEM calculations: what building control needs and when

Quick answer

SBEM calculations are how a new non-domestic building, or an extension big enough to be treated as one, shows building control it meets its Part L energy targets. In England the design-stage notices are due by the day before work starts and the as-built ones within five days of completion, the deadline for the on-construction EPC too. SBEM is the government’s tool; an approved dynamic simulation model is the alternative.

The first figures are due before work starts on site, so commission the calculation while the design can still change.

What is an SBEM calculation?

It is the Part L energy check for a new non-domestic building. The software models the building’s geometry, fabric and services, estimates its energy use and carbon dioxide emissions, then does the same for a notional twin of the same size and shape with standardised fabric and services, which sets the targets.

England sets two targets in the Building Regulations 2010, a CO2 emission rate (regulation 26) and a primary energy rate (regulation 26C), and a new building may exceed neither. The notice of approval of 24 March 2026 requires both, as designed and as constructed, to be worked out in SBEM or in an approved dynamic simulation model (DSM). The commercial EPC glossary defines the term.

When does building control need SBEM calculations?

For most new buildings, and for an extension large enough to count as one: Approved Document L uses the new-building route where the extension’s floor area exceeds both 100 square metres and 25% of the existing total useful floor area. Its exemptions include places of worship, stand-alone buildings under 50 square metres and temporary buildings planned for no more than two years. The refurbishment and extension guide covers smaller work.

In England, outside higher-risk building work, the person carrying out the work must give building control:

  1. By the day before work starts: the target and as-designed CO2 emission rates with the list of specifications (regulation 27), the same for primary energy (regulation 27C), and confirmation that high-efficiency alternatives such as heat pumps have been assessed and the analysis documented (regulation 25A). Approved Document L pairs these with the commissioning plan.
  2. Within seven days of the final air pressure test: the results (regulation 43).
  3. Within five days of completion: the as-built rates and any specification changes (regulations 27 and 27C), and notice that the owner has the EPC, quoting its register reference (EPC Regulations 2012, regulation 7A).

Higher-risk buildings send the design-stage notices with the application for building control approval.

What is the difference between the design-stage and as-built calculation?

The inputs. The design-stage run uses design values; the as-built run uses the building as constructed, with every site change to the list of specifications and the air permeability measured in the pressure test. One approved tool must produce every rate, and both targets must be met each time.

Two people sign the as-built report: the energy assessor, for the accuracy of the calculations, and the client, usually the developer, confirming the building matches its specifications. So site substitutions, such as a different heat pump or glazing, need to reach the assessor as they happen.

How do SBEM calculations relate to the BRUKL report and the on-construction EPC?

The BRUKL report is the format Approved Document L names for the figures: both stages may be reported in it, as a standardised output of the approved software. The BRUKL report guide explains it.

The EPC is a separate certificate from the same approved methodology, due in the same five days, and government guidance says no completion certificate is issued until building control is satisfied the EPC has been given. Ask whether one quote covers both; EPCs for new commercial buildings explains the duty.

When is a dynamic simulation model used instead of SBEM?

When the design has features SBEM cannot model adequately. Approved Document L allows SBEM where it can model the design adequately, or another approved tool, and expects the submission to show the chosen tool suits the building. One tool has to carry the project from design stage to as-built, so decide before the first run.

The SBEM Level 3 and 4 versus DSM guide covers which buildings usually need a DSM. And SBEM does not size plant: the NCM website says it should not be used for system sizing.

What changes with the 2026 Approved Document L?

It is published but not yet in force. Approved Document L, Volume 2 (2026 edition), retitled "Energy and greenhouse gas emissions", was published on 24 March 2026 and revised on 8 September 2026. It takes effect in England on 24 March 2027, or 24 September 2027 where the work is higher-risk building work.

Outside higher-risk work, Building Circular 01/2026 keeps the earlier rules for projects notified before 24 March 2027 by building notice, initial notice or full plans that start before 24 March 2028, and the notice of approval lets them use the earlier methodology; others will use the 2026 NCM for England. Among the listed changes:

What should you have ready for the assessor?

Real data: the NCM website says its software’s defaults are conservative, closer to existing than new buildings, and there to be replaced; building control can request evidence for values entered. For the design-stage run, gather:

For the as-built run, add the record of site changes and the pressure test result.

What should a quote for SBEM calculations cover?

Ask each quote to state:

Compare quotes line by line: one that omits the as-built run or the EPC is a smaller job. Once drawings and a specification exist, you can send the details through the enquiry form.

What is different in Wales and Scotland?

Wales applies its own versions of the same regulations: the Welsh Ministers approve the targets, primary energy is notified under the Welsh regulation 27A rather than England’s 27C, and the deadlines match. Wales’s 2026 Approved Document L, Volume 2 takes effect on 4 March 2027, except for work notified earlier that starts before 3 March 2028 (circular WGC 006/2026, 7 April 2026). The on-construction EPC rule covers both nations.

Scotland requires a building warrant before any work starts, and the Scottish Government’s warrant checklist lists SBEM as required for new non-domestic buildings. Its energy standards, in section 6 of the Technical Handbooks and last revised in 2023, set a delivered energy target. Design changes after approval need an amendment of warrant, and occupying a new building before its completion certificate is accepted is an offence. A consultation on new standards closed on 16 October 2026; its contents are proposals.

Wherever the building is, send the details through the enquiry form.

Sources

Send your building details

By submitting you agree to our privacy policy. We never sell your details. We reply by email.

Common questions

Who gives the SBEM figures to building control?

The person carrying out the building work, under regulations 27 and 27C. Building control may also accept, as evidence the targets were met, a certificate from an energy assessor accredited for EPCs on that type of building.

What happens if the as-built figures fail?

The building must meet its targets at completion too, so a fail has to be fixed, by correcting inputs with evidence or improving the specification, before the as-built notice can show compliance.

Will the results predict energy bills?

No. Approved Document L says compliance outputs are not suitable for direct use as energy forecasts, and wants a separate forecast by fuel in the log book of any new building over 1,000 square metres.

Does SBEM cover the flats in a mixed-use scheme?

No. Approved Document L Volume 2 covers the non-domestic parts and heated common areas, and the NCM website says self-contained flats are assessed with SAP, the method for dwellings.

Send details
Send details